Here is a concrete example showing how props and formwork work together, step by step, for a common construction task: pouring a reinforced concrete suspended slab (e.g., a second-floor ceiling/floor) in a multi-story building.
In this example, we assume the ground floor slab has already been poured and cured.
Scenario: Pouring a Suspended Concrete Slab (5m × 5m) at 3m Height
Goal
Create a horizontal concrete slab 3 meters above the ground.
-
Formwork creates the flat, smooth underside of the slab.
-
Props hold that formwork up against gravity while the wet concrete (which is extremely heavy) cures.
Step 1: Layout and Setup
Props (Vertical Support)
-
Acrow Props (adjustable steel props) are selected for this medium-height application.
-
They are arranged in a grid pattern (e.g., every 1.2 meters in both directions) to evenly support the load.
-
Each prop is adjusted to the correct height (approximately 2.9 m to allow for the thickness of the formwork and beam).
-
Base plates are placed under each prop to distribute the load onto the ground floor slab.
-
Horizontal bracing (scaffolding tubes or frame braces) is clamped between props to prevent lateral buckling under load.
Formwork Deck
-
Plywood sheets (18–21 mm thick phenolic film-faced plywood) are laid across the tops of the props.
-
Joists (timber or aluminum beams) are placed between the props and the plywood to distribute the load evenly and prevent the plywood from sagging.
-
The plywood sheets are butted tightly together and sealed with tape or caulk to prevent cement slurry leakage.
Step 2: Integration at Beams and Edges
Edge Formwork
-
Along the perimeter of the slab, vertical timber formwork (called “edge forms” or “stop ends”) is installed to contain the concrete.
-
These edge forms are propped horizontally using raking props or nailed to the supporting structure to resist the outward pressure of the wet concrete.
Beam Formwork
-
If the slab includes a dropped beam (a deeper structural element), separate beam formwork is created.
-
Beam sides (vertical plywood panels) are clamped together and supported by props directly underneath the beam.
-
The slab formwork sits on top of or butts into the beam formwork.
Step 3: Load Transfer – How Props Support Formwork
When the concrete is poured:
-
Wet concrete weighs roughly 24 kN/m³ (approx. 150 lbs/ft³). A 200 mm thick slab exerts approximately 4.8 kN/m² (100 lbs/ft²) just from the concrete weight, plus formwork self-weight and live loads (workers, equipment).
-
This load is transferred:
-
From concrete → plywood (formwork)
-
From plywood → joists
-
From joists → prop heads
-
From props → ground floor slab (or ground)
-
-
The props remain in place until the concrete reaches sufficient compressive strength (usually 70–75% of design strength, typically after 7–14 days depending on mix and temperature).
Step 4: Stripping (Removal)
Props are not all removed at once.
-
Initial strip: After the concrete cures, the formwork deck (plywood and joists) may be removed while the props remain in place. This is called “propping back.”
-
Prop removal: Props are systematically removed starting from the center of the slab and working outward, following a sequence that ensures the slab is not overstressed before it reaches full strength.
-
Reuse: The props and formwork panels are cleaned, repaired if necessary, and moved to the next floor for reuse.
Visual Summary
| Element | Role | Example in This Scenario |
|---|---|---|
| Formwork (Plywood) | Molds the concrete | Creates the smooth underside of the slab. |
| Formwork (Joists) | Distributes load | Aluminum or timber beams spaced every 0.6 m. |
| Props | Vertical support | Acrow props on a 1.2 m × 1.2 m grid, braced together. |
| Edge Formwork | Contains concrete at slab perimeter | Plywood secured with raking props or clamps. |
| Beam Formwork | Forms deeper structural elements | Separate panels with dedicated props underneath. |
Why This Matters
Without props:
-
The formwork deck would collapse under the weight of wet concrete (often 50–80 tons for a typical residential slab bay).
Without formwork:
-
The props alone cannot shape the concrete or provide a finished surface.
Together, the formwork defines the geometry, and the props provide the structural stability to resist gravity until the concrete becomes self-supporting.
If you would like, I can also illustrate a different scenario—such as a column and beam system or wall formwork with raking props—to show how the relationship changes depending on the structural element being poured.