Give an example of how props and formwork are used together

2026-03-26 Visits:10,390

Here is a concrete example showing how props and formwork work together, step by step, for a common construction task: pouring a reinforced concrete suspended slab (e.g., a second-floor ceiling/floor) in a multi-story building.

In this example, we assume the ground floor slab has already been poured and cured.


Scenario: Pouring a Suspended Concrete Slab (5m × 5m) at 3m Height

Goal

Create a horizontal concrete slab 3 meters above the ground.

  • Formwork creates the flat, smooth underside of the slab.

  • Props hold that formwork up against gravity while the wet concrete (which is extremely heavy) cures.


Step 1: Layout and Setup

Props (Vertical Support)

  • Acrow Props (adjustable steel props) are selected for this medium-height application.

  • They are arranged in a grid pattern (e.g., every 1.2 meters in both directions) to evenly support the load.

  • Each prop is adjusted to the correct height (approximately 2.9 m to allow for the thickness of the formwork and beam).

  • Base plates are placed under each prop to distribute the load onto the ground floor slab.

  • Horizontal bracing (scaffolding tubes or frame braces) is clamped between props to prevent lateral buckling under load.

Formwork Deck

  • Plywood sheets (18–21 mm thick phenolic film-faced plywood) are laid across the tops of the props.

  • Joists (timber or aluminum beams) are placed between the props and the plywood to distribute the load evenly and prevent the plywood from sagging.

  • The plywood sheets are butted tightly together and sealed with tape or caulk to prevent cement slurry leakage.


Step 2: Integration at Beams and Edges

Edge Formwork

  • Along the perimeter of the slab, vertical timber formwork (called “edge forms” or “stop ends”) is installed to contain the concrete.

  • These edge forms are propped horizontally using raking props or nailed to the supporting structure to resist the outward pressure of the wet concrete.

Beam Formwork

  • If the slab includes a dropped beam (a deeper structural element), separate beam formwork is created.

  • Beam sides (vertical plywood panels) are clamped together and supported by props directly underneath the beam.

  • The slab formwork sits on top of or butts into the beam formwork.


Step 3: Load Transfer – How Props Support Formwork

When the concrete is poured:

  1. Wet concrete weighs roughly 24 kN/m³ (approx. 150 lbs/ft³). A 200 mm thick slab exerts approximately 4.8 kN/m² (100 lbs/ft²) just from the concrete weight, plus formwork self-weight and live loads (workers, equipment).

  2. This load is transferred:

    • From concrete → plywood (formwork)

    • From plywood → joists

    • From joists → prop heads

    • From props → ground floor slab (or ground)

  3. The props remain in place until the concrete reaches sufficient compressive strength (usually 70–75% of design strength, typically after 7–14 days depending on mix and temperature).


Step 4: Stripping (Removal)

Props are not all removed at once.

  1. Initial strip: After the concrete cures, the formwork deck (plywood and joists) may be removed while the props remain in place. This is called “propping back.”

  2. Prop removal: Props are systematically removed starting from the center of the slab and working outward, following a sequence that ensures the slab is not overstressed before it reaches full strength.

  3. Reuse: The props and formwork panels are cleaned, repaired if necessary, and moved to the next floor for reuse.


Visual Summary

Element Role Example in This Scenario
Formwork (Plywood) Molds the concrete Creates the smooth underside of the slab.
Formwork (Joists) Distributes load Aluminum or timber beams spaced every 0.6 m.
Props Vertical support Acrow props on a 1.2 m × 1.2 m grid, braced together.
Edge Formwork Contains concrete at slab perimeter Plywood secured with raking props or clamps.
Beam Formwork Forms deeper structural elements Separate panels with dedicated props underneath.

Why This Matters

Without props:

  • The formwork deck would collapse under the weight of wet concrete (often 50–80 tons for a typical residential slab bay).

Without formwork:

  • The props alone cannot shape the concrete or provide a finished surface.

Together, the formwork defines the geometry, and the props provide the structural stability to resist gravity until the concrete becomes self-supporting.


If you would like, I can also illustrate a different scenario—such as a column and beam system or wall formwork with raking props—to show how the relationship changes depending on the structural element being poured.